Commissioning mooring system LNG Terminal Stade
18 March 2024
Another successful project in the books! This time, we commissioned the complete mooring system for Germany's Stade LNG Terminal, located in the north of the country.
This terminal, known as the Hanseatic Energy Hub, will play an important role in facilitating LNG imports and securing Germany's supply.
We're proud to have played our part in this important project. The first arrival of the FSRU Transgas Force at the new jetty is expected by the end of March. To ensure its safe and efficient mooring, we manufactured, delivered, and commissioned all the necessary equipment:
- - All 150T and 125T triple Quick Release Mooring Hooks (QRH) with capstans
- - Remote release and Load Monitoring System (MLMS)
- - Environmental Monitoring System (EMS)
- - Control panel featuring our MoorControl software
A big thanks to the project team at Depenbrock Bau for their excellent cooperation throughout the process!